Monument
The monument plaques have finally been installed. They look really good. This is the right one with the house number. |
|
|
Monument
And the left one with the name of the house. |
|
|
Septic Field
They started installing the septic tank today. They made a lot of progress. Here you can see the distribution box--the black box in the center--and the pipes running to the drain field. |
|
|
Septic Field
This is one of the four 100'-long drain tiles for the septic field. The other three are to the right and already partially covered. They are using a new, no-gravel insert for the field. It really goes in fast. |
|
|
Septic Field
This is the line from the house--the house is right behind my back. You can see the top of the septic tank. It is a 1200 gallon concrete tank. I was a little surprised. I expected a plastic tank. |
|
|
|
Driveway
They dumped the gravel on the driveway yesterday and compacted it today. |
|
|