Brick

Got some major scafolding going on now. This is the kind that can be cranked up and down to lift the bricks.

Brick

They made a lot of progress today. I decided the brick did look good. I actually wish I had picked a dark color mortor now that I see it like this. But this is just wet and will dry much lighter.

Brick

Got a good section of the back done too. The brick on the back only goes up to about 3/4 of the door height.

Brick

Brick

Just as we got there tonight, they were delivering more brick. Don't know if this is all of it or not. Builder has ordered 15,000.

Plumbing

More plumbing work is done. I took most of these pictures not because they are interesting, but so we would know where the plumbing is when they close up the walls. This is the laundry room.

Plumbing

The waste stack coming down from the guest bath.

Plumbing

Powder room

Guest Bath Shower

The shower has arrived for the guest bath. They had cut studs out of two walls to fit it into the bathroom.

Plumbing

Guest bath toilet and vent from below.

Plumbing

Guest bath vanity

Plumbing

Master bath vanity

Plumbing

Drain for the master bath shower.

Chase cutout

The HVAC crew has cut out the floor in the chase between the first floor and basement so they can run the ducts.

Chase Cutout

Also between the first and second floors.

HVAC

They have started putting in the duct work. I really like the flexible ducts they are using. They are heavily insulated. This is in the attic leading to the upstairs rooms.

HVAC

This is in the bonus room. They put three registers in this room.

Windows

All put two windows are now in. They still have to do the garage and one of the windows in the nook. But, when they picked up all the wrong windows, they also took some of the right ones! But their just at the local warehouse.

Soffits

They now have the soffits, facias, and friece boards for the front porch almost done.